Service pole


The service power pole is used during the modernization of the line. It is used „pole for pole”. The great advantage of these poles is that they can be stored in any energy area. Power can be restored temporarily when no special equipment is involved. This can be done by the crew of the energy emergency.

OPTION – 2-SEGMENT ENERGY SERVICE POST

Diagram of the bypass as an ad hoc method during modernization, bringing measurable benefits for the LV line operator

SERVICE ENERGY POLE WITH AN EXHAUST – FUNCTIONAL ON THE BASIS

SERVICE ENERGY POST
The order of placing the service pole:

  • Place the support on the ground and level it, selecting the ground under it until the maximum contact with the ground is obtained (do not sprinkle it);
  • Put one layer of the standing boards on the base;
  • Screw the carrying bolts and the plate to the base as shown in the drawing No. 1;
  • Assemble the service pole as a whole by pressing the pin fi 8 in the hole to block both segments in the middle and connect the pole with the bottom plate of the bracket using the hinge pin;
  • Place the service pole in a vertical position, setting it in a vertical position using the nuts on the carrying bolts;
  • Lock the bolt connection by tightening the nuts with the torque shown in the figure;
  • Place the remaining 5 layers of the standing boards on the load-bearing base.

ATTENTION! The service power pole will be able to transfer the load with the assumed bending moment under the following conditions:

  • The strength of the soil under the stall will be equal to or greater than 31.8 kN / m2
  • The stall will be loaded with six layers of siding plates, each 600x850x60mm
  • The outer dimensions of the base of the parking lot will be 1530x1530mm

POST BASE PLAN
Correction consisting in removing or adding plates is unacceptable.